Hi everyone.
I have a bit of situation. I need to cancel one business process in case of triggering the other , but i cannot diactivate it permanently.
1st BP: signal if account stage 4 is modified - create and activity to create a prospect.
But not all users do it properly as it meant to be and sometimes they create a prospect right away and I need that stage added automatically.
BUT if 2d BP (which is signal "prospect is added" then account stage = prospect) triggered, then signal of the 1st BP triggered also and activity will be created all over again.
therefore, i have a full circle
Thanks.
Like
Hello!
Unfortunately we do not have basic functionality, which we could recommend to cancel the business process by another business process. In such cases, it could be developed only by custom script.