Hello 

When creating a new Task the system automatically sets the task duration 30 minutes. How can I change this default value?

 

There is an older question about it, but I can't find that line that is mentioned there  

 

Thanks in advanced for your help!

Like 0

Like

3 comments
Best reply

Hello Cesar,

 

Unfortunately, there is no option to change the default value anymore.

As a workaround, you are able to change the duration after creating the task.

 

Thank you,

Artem. 

Hello Cesar,

 

Unfortunately, there is no option to change the default value anymore.

As a workaround, you are able to change the duration after creating the task.

 

Thank you,

Artem. 

Hello Artem,

 

In version 8.0.10, is it possible to change the default value assigned to the duration of activities?



Thank you,

Andreia

 

 

Hello Andreia,

 

Unfortunately, this option is still not available at the moment. However, a task has already been registered in our R&D team to consider and implement such a feature in future releases.

 

 