Dear mates,

I'm trying to modify the DCM Opportunity.

I want to add a step before the first step.

But when i create a new step, the opportunity goes automatically to the old first step. i look everywhere i can, but i can't find why.

Does anybody have an idea please.

Thanks,

Nicolas

Like 0

Like

2 comments

Dear Nicolas,

In OOB system "stage" column is required when opportunity is created. You should check what stage is used when opportunity is created: http://prntscr.com/pqzl32

Dear Angela,

Effectively, i add the stage on the mini-page, and the stage used when opportunity is created is not the DCM first step (it is "En cours").

i have to find where the developper has forced the stage on the mini-page to a specific step.

=> Solution:

The default opportunity's stage was defined on the Opportunity Object.

Thank you Angela !